A recent tour of the new Rogers High School. Credit: Newport Public Schools

The School Building Committee for Newport’s new Rogers High School, which is led by Becky Bolan and Louisa Boatwright, has released its 142nd update, highlighting recent progress and upcoming milestones.

With the building handover just three months away, construction activity is in full swing. The first phase of exterior work is underway, including drainage installation on Wickham Avenue. Inside, crews are busy with tiling, painting, electrical systems, room assignments, equipment installation, and technology setup. The building is now weather-tight, marking a key construction milestone.

High school teachers are already preparing for the move. They’ve received packing boxes and are following a schedule from Principal Vance to get ready for the transition starting in early June.

The Newport School Committee is looking into keeping the NACTC building, which houses automotive and cosmetology programs. They’re meeting on Feb. 26 at Pell Elementary School to discuss this option.

On Feb. 24, the School Building Committee will meet at Pell Elementary to review new change orders and get updates from vendors. The public can attend in person or watch the livestream on the Newport Public Schools YouTube channel.

Project leaders are working on setting a date for the ribbon-cutting ceremony and open house tours, expected in August.

Gilbane Construction Company is evaluating how keeping the NACTC building might affect the project timeline. Early reviews suggest work in or around the NACTC building may not be finished before the school year starts in September.

The current schedule aims to complete the new building by June 2025. Demolition of the old building and final site work will continue through August 2026.

Read The Full Update Below

February 21, 2025 

SBC Update # 142 

Yes, we are already rounding up the month of February and there is so much happening. 

We have about three months before the keys to the new RHS are to be handed over to us.  Everywhere, inside and outside of the building, activity is ramping up as the first phase of the  outside site work is underway, the drainage for water retainage areas on Wickham Ave is being  installed, and the interior of the building is bustling with work centered around the tiles, painting,  electrical, room assignments, equipment installation, technology implementation, shelving  rooms, and much more. The building is finally weather tight-Woo-Hoo!! Each week we have an  ongoing list of details to be addressed with items that need attention. Our high school teachers  already have their packing boxes. They along with the Superintendent’s Office are under a  schedule provided by Principal Vance of dates and timelines to be ready for the transitioning  process to begin in early June. Director Young is wrapping up the furniture purchases with Ted  Tolis from SLAM, Principal Vance is working diligently on the Fitness Room layout and  equipment, and our community supporters are helping us with donations and much more! All of  us are wearing many, many hats as the project is zooming forward. 

Our Newport School Committee is also very busy seeking ways to keep the NACTC building to  save our automotive and cosmetology programs from having to move off campus. This action  would also provide much needed office spaces for administration. Gilbane has recently provided  cost estimates to us regarding keeping the NACTC building and next Wednesday, February  26th at Pell Elementary School at 5:30pm, the NSC will meet to consider moving a plan forward  to keep the NACTC building. Let’s keep our fingers crossed that all goes well.  

Before then however, on Monday, February 24, 2025 there will be a school building committee  meeting. We are looking forward to seeing everyone at the Pell Elementary School at 5:30 as  we review some new change orders and hear updates from our vendors. We hope everyone  tunes in https://www.youtube.com/@newportpublicschools/streams or swings by to learn more  about this great project that our community supported and is looking forward to seeing in the  near future. At our next update, we will try our best to announce a “Save the Date” for our ribbon  cutting, and Open House for tours that will take place in August. So stay tuned for more  information as the weeks unfold. These are exciting times! 

As always, here are our other updates for the week. 

Calendar: 

Our next meeting will be Monday, February 24th at 5:30 pm at Pell.  

GILBANE UPDATE: 

Here is the January monthly update from Aleita at Gilbane.

As mentioned above, Gilbane (GBCo) is taking a deeper dive into how the scope of work at the  NACTC building impacts the schedule. Initial review suggests that GBCo would not be complete  with work within or around the NACTC building prior to school starting in September. NPS has  already expressed the need to occupy the building at the start of the school year and will work  with GBCo on fencing and staging to ensure the building stays open. More info to follow after  the drawings are completed with NACTC open to our students and administration if the NACTC  building is retained.  

Here is the Gilbane Two Week Look Ahead: Thank you Billy and Kristin! Wednesday 2/19/25 through Tuesday 03/04/25 

DiGregorio Sitework 

Erosion Control and Site Maintenance / Cleanup Operations around entire site Working on Water and Drainage 

Planning for February Break Work – Trade Parking @ Bus Loop 

(2/15 through 2/23) 

-Work in West parking Lot 

-Cut & Cap Water Feed to Hydrant on East Elevation 

Plan for April Break Work 

(4/19 thru 4/27) 

Continue logistic and schedule development for Summer Work 

Capasso Masonry 

Caulking / Punch List 

Shepard Steel Structural & Misc Metals 

Handrails 

Greenwood Roofing 

Edge Metal & Coping / Gutters 

Punchlist 

Century Drywall 

Frame / Board & Tape 1stFloor 

Continue FRP In Kitchen Areas 

Plywood in Gym 

H.Carr Ceilings 

Re-work Tectum panels Construction Tech 

Grid & Tile All Floors 

Shea Painting 

Classrooms and Corridors 

Stairwell Railings & Stringers  

Chandler Glass 

Continue Exterior Curtain Wall / Interior Glass 

Ruggieri Flooring 

LVT Install Floors 1 

Pavilion Tile1st 

Floor Bathrooms / Corridor

Northeast Interiors 

Classroom & Lab Casework All Floors 

Tavares 

Toilet Partitions & Bathroom Accessories 

Walker Specialties 

Install Window Shades 

Arden Engineering 

Overhead in Kitchen 

Finishes 2nd& 3rd 

Floors – Start on 1st 

Hot Water Heaters / Gas to Lab Casework 

Rossi Electric 

Overhead Electrical – Low Voltage Rough-In 1stFloor 

Auditorium, Construction Tech & Student Commons Overhead 

Main Electrical Rooms 

Energize Lights and Power Upper Floors 

Delta Mechanical & Fire Suppression 

Mechanical piping install / Hang & Tie – VRF Units 1st Floor Overhead 

Install Ductwork 1stFloor 

Fire Protection @ Ceilings, Testing 

Other Items: 

NACTC / Civil Drawings pricing after the NACTC decision is finalized 

Pending Authorization to Proceed: Aleita Hall (Gilbane) 

1. The following changes are pending approval:  

2. ATP-123 Provide Site Furnishings – Issued 01/28/2025 – On HOLD. C.Jermain  coordinating with the City.  

3. ATP-125 Provide Granite Curb at Old Fort Parking Lot – Issued 01/31/2025 – Approved  at CORG Meeting 02/11/2025. Pending SBC Approval 

4. ATP-127 Site Signage – Issued 02/14/2025. SLAM/Downes review 

Pending Changes: Aleita Hall (Gilbane) 

1. Dedication Plaque 

2. Site Plantings by Phase 

3. Vinyl Graphic at Student Commons 

4. Bulletin 036 – Dumpster Enclosure 

Potential Changes: Aleita Hall (Gilbane) 

1. No update 

SLAM UPDATE: 

Design A/E update: Catherine Ellithorpe and Ted Tolis (The SLAM Collaborative) SLAM is preparing the following documents:

1. Bulletin 035 – NACTC Remaining. SLAM to issue drawings for new water meter  assembly in NACTC.  

2. Bulletin 037 – Adding Bollards ONGOING 

3. Student Commons Wall Graphic Design ONGOING 

4. Dedication Plaque – ONGOING 

SLAM continues to work on: 

1. Submittals 

2. RFI responses 

3. Field Visits/Reports 

RIDEM: Catherine Ellithorpe (The SLAM Collaborative) 

1. SLAM to review status of final RIDEM submission after NACTC re-design decision is  finalized. 

2. SLAM to finalize RIDEM application with Pare 

OPM -DOWNES UPDATE 

Utilities: Deb Reading (Downes Construction-OPM) 

The following utility updates are: 

1. Electrical: Connected and turned on 

2. Gas: Connected 

3. Communications: Cox is on site working with IT 

4. Water: Connected  

Neighbor Communication: Deb Reading (Downes); Aleita Hall (Gilbane) Questions were recently submitted regarding the project. See the questions below with the best  answers we are able to provide at this time.  

1. Could you outline what work will remain and the process for finishing New Rogers and  its environs?  

The Gilbane timeline is: 

a. New RHS Building Completed by June 2025 

b. Demolition of old building begins through November 2025 

c. Final Sitework – August 2026 

2. Who will be responsible for the supervision and completion of this work, School Building  Committee, School Board, or is the City in charge/responsible?  

a. The SBC, along with the Newport School Committee, will be responsible for the  completion of the school building project. 

3. When do you expect the project to be “done and dusted” – Plaques hung and contractors  gone.

a. The building will have plaques hung by August 2025. The contractors will be  onsite for another year completing the utility work and Phase II of the  

landscaping for the school building project. 

4. Will the NACTC building be retained?  

That decision is not final yet. It is to be voted on at the next NSC meeting on February  26th; 5:30pm at Pell School.  

a. How much will the retention cost? See the letter from Co-Chair Bolan to the NSC  regarding retaining the NACTC building. NSC letter 

b. What advantages does its retention bring? The automotive and cosmetology  programs for students stay intact and on campus. The school budget does not  have to finance offsite bussing or rental of other properties to keep the programs.  The Superintendent’s office and administration may avoid renting additional  space, and there may be additional office space to rent out. 

c. It seems quite late in the building process to be worrying about changes like the  fate of the NACTC building. Why? The newly elected members of the NSC  made it a priority to keep the building. They, along with other members of the  NSC, after hearing from many alumni and residents during their election  

campaigns of community members’ desire to keep the programs on campus- and  not interrupt the programming for students.  

5. What is the current size of the “PILE”? Current volume in the stockpile is estimated to be  50,000 CY. Total volume to be added is estimated to be ~7,000 CY pending final  drawings and earthwork calculations. 

a. What is the plan for its disposition/schedule? The SBC plan continues to use as  much of the soil as possible during the landscaping and other projects after the  new school building is completed and open. That has not changed

b. Who is responsible for it? In a letter to the City, RIDEM, RI Department of  Environmental Management stated the City has oversight of this. At this time, we  believe the City is progressing with testing the old dump, using the consultant  VHB, and will determine next steps once VHB has issued their report.  

6. Does the City plan to use any of the excess land around the school for amenities like a  Dog Park, Pickleball Court, Bike Path, BMX Track? This needs to be deferred to the  City. 

a. Has the Open Space Committee looked at this? Not that we are aware of at this  time. 

Stockpile/Existing Soil Reuse: Aleita Hall (Gilbane); Ted Tolis (SLAM); Tim Theis (PARE)  and Deb Reading (Downes) 

1. Discussion on hold pending NACTC decision. The goal of the team is to reuse as much  soil as possible.

Owner Provided Equipment: FFE/ EPlus (Gilbane, SLAM, Downes, & NPS) Downes provided the following updates: 

1. FF&E – Pending RIDE Approval which would then allow the PO to be issued. It was  noted that SLAM/Downes responded to RIDE comments.  

2. e-Plus – Coordination meetings to re-commence this month. 

3. Movers – no further update provided this date 

4. Gym Equipment Bidders – Downes provided NPS with quotes for athletic equipment 

Consolidated Action Item List: 

Director Young and Principal Vance will continue to meet with the “Detail” working group to  facilitate the equipment moves, staff room assignments, student building tours, and other detail  matters that require consideration before the school year ends and the new one begins. Co Chair Bolan is participating in as many meetings as possible. Dr. Jermain and others are available to confer when requested.  

So, February is wrapping up- and with it we hope for warmer weather and sunshine. Let’s hope  for an early spring! We look forward to seeing many of you at our SBC meeting this Monday at  5:30 at Pell Elementary School. The agenda for the meeting is HERE. Thank you again to all  our members and their hard work. The finish line is now in sight- and with it a ribbon cutting in  August. Stay tuned for more information and again- Thank you everyone for your support and all  the hundreds of hours you have all given for the once in a lifetime project. 

Have a wonderful weekend! 

Becky and Louisa

Ryan Belmore is the owner and publisher of What's Up Newp. He took over the publication in 2012 and has grown it into a three-time Rhode Island Monthly Best Local News Blog (2018, 2019, 2020). He was named LION Publishers Member of the Year in 2020 and received the Dominique Award from the Arts & Cultural Society of Newport County the same year. He has been awarded grants for investigative and community journalism, and continues to coach and mentor new local news publications nationwide. Ryan...

Leave a comment

We welcome relevant and respectful comments. Off-topic comments may be removed.